CORE 12-10-12· Initial findings from Peter L showed that we don't have enough elevation difference to have the walkout arrangement shown on all out drawings...easily.o If the front of the school is at 784 and there is no articulation between it and the front of school building and the studio/shops then the back of the shops will need...
Greetings Solar Team ~Attached is the current version of the Yestermorrow campus with the center of gravity now returned to the Alpen Inn. This change was driven by a zoning requirement that no more than 25% of existing buildings may be destroyed. Budget and schedule also played a role. So this is great news for those who monitor our solar...
CORE 11-26-2012· John provided a site plan for consideration.o Kathy considered the implications of path and snow. Mentioned the effect that pedestrians have on slowing traffic. Suggested minimizing the paths other than what's already paved within the lot. And then the connection to the main building would be the only additional...
· Pre- McCain (Lazorchak) plan reviewed.· Preliminary path designs submitted (thank you Kathy and Kate)We anticipate a lot more work in this area after we have our topo back from Peter L.· Greenhouse inclusion was discussed pro...
CORE 10-12-12 Minutes….taken on the run and not edited (apologies in advance for any misquotes)KIN for Five Minutes (Quality and Direction of our Process) (starting with a summary of Jim Martin's presentation at the BigPic)Some basic thoughts concerning our current process:1. Our relationship with the DRB.a. Risk credibility if we...